What is a work order in manufacturing?
A shop floor does not start on good intentions. It starts on a document that says what to build, how many, from which components and by when. That document is the work order. Here is what it is, the fields it has to carry, a filled-in example, a template to download, its full life cycle, and how ERP and MRP systems handle it.

TL;DR
- A work order is the internal document that authorizes a shop floor to build a given item, in a given quantity, by a given date.
- It pulls together the item, the quantity, the components to consume (the bill of materials), the operations to run (the routing), the work centers and the dates.
- It originates either from a sales order (make to order) or from a stock replenishment need, most often suggested automatically by MRP.
- Its life cycle runs from planned to closed, and closing it is what produces the time, material and cost variances.
You want to know what a work order actually looks like, which fields belong on it, and how it is tracked from release to closing. That question shows up the moment a shop grows past the point where everyone simply knows what to build next. Here is the definition, the full field list, a filled-in example, a template to download, and the point where a spreadsheet stops being enough.
Two meanings, one term
In manufacturing, a work order authorizes production of an item. In facilities and asset management, a work order authorizes a maintenance job on a machine or a building, and it is handled by a CMMS rather than an ERP. This page covers the manufacturing sense.
What is a work order, exactly?
A work order, sometimes called a manufacturing order or a production order, is an internal document that authorizes and organizes the production of an item. It is not addressed to a customer or to a supplier: it is the company instructing itself. Vendor documentation describes it as the record that connects production demand to materials, routing operations, labor, quality, finished goods and actual manufacturing cost.
Its purpose comes down to two words. Authorization first: until the work order is released, the shop floor consumes neither material nor hours. Traceability second: once released, it becomes the record against which logged time, actual component consumption, good quantities and scrap are posted. Without it, production is an activity nobody can cost after the fact.
Work orders come from several places, and the origin changes how you manage them. In make to order, the work order derives from a specific sales order and carries its number, which is what lets you answer “where is my order”. In make to stock, it exists to rebuild an inventory level, and it is usually MRP that proposes it, alongside the purchase orders for bought-in parts. Rework, prototypes and internal tooling requests are common sources too.
What fields does a work order need?
There is no legally mandated field on a work order: it is a working document, not an invoice. There is, however, a minimum set without which the shop floor has to come and ask questions, and a work order that triggers questions has failed at its job. Here is the core.
| Field | What goes in it | Why it has to be there |
|---|---|---|
| Work order number | A unique, sequential identifier | It is the key that time, materials and scrap are posted against |
| Item to build | Part number and description of the finished good or subassembly | Removes any ambiguity between two close variants |
| Quantity and unit | Quantity released, with the unit of measure | Drives component requirements and shop load |
| Source | Sales order (with its number) or stock replenishment | Lets you arbitrate priorities when the shop is saturated |
| BOM and revision | The component list, in the correct revision | A stale revision pulls the wrong parts out of the stockroom |
| Routing and revision | The sequence of operations, with setup and run time per unit | Used to schedule, then to measure the time variance at closing |
| Work center | Machine, cell or line where each operation runs | Without it there is nothing to schedule against |
| Release and due dates | When the shop gets it, when the item is expected in stock | Fixes the work order’s place in the production schedule |
| Status | Planned, released, in progress, on hold, completed, closed | Shows at a glance what is actually committed |
| Completed and scrapped quantities | Posted during and after execution | The raw material of variance analysis |
On top of that core, industries add what they need: supporting documents (drawings, work instructions, inspection plans), tooling to be mounted, a lot or serial number in regulated sectors, and the standard cost that will serve as the baseline at closing.
Good habit
Always print the revision of the BOM and routing on the work order, not just their reference. That is what lets you explain, six months later, why two work orders for the same item did not consume the same parts.
What does a filled-in work order look like?
Nothing beats a populated record for seeing what the fields do in practice. Take a bicycle shop that owes a customer 40 city bikes and also builds wheels and frames to stock. Three work orders coexist, at three different stages.
| WO no. | Item | Qty | Source | Release | Due | Status | Done / scrap |
|---|---|---|---|---|---|---|---|
| WO-2026-0148 | BIKE-CTY-26, city bike | 40 | Sales order SO-5821 | Oct 20, 2026 | Oct 27, 2026 | Released | 0 / 0 |
| WO-2026-0149 | WHEEL-700C, built wheel | 120 | Stock | Oct 19, 2026 | Oct 23, 2026 | In progress | 64 / 2 |
| WO-2026-0150 | FRAME-ALU-M, frame size M | 60 | Stock | Oct 22, 2026 | Oct 30, 2026 | Planned | 0 / 0 |
Three things read straight off that table. The bike work order is released but not started, because it is waiting on wheels: its October 20 release only makes sense if WO-0149 holds its October 23 date. The wheel work order shows 2 scrapped units out of 64 built, a variance that will have to be explained at closing. The frame work order is planned, so it holds a slot in the schedule, but it has committed neither material nor hours.
Work order template 2026
CSV file, opens in Excel, Google Sheets or LibreOffice. Eighteen columns, three example work orders to overwrite, no macros.
The template carries the ten core fields plus the shop floor feedback columns (quantity completed, quantity scrapped, hours logged) and a notes column. It is deliberately a table and not a form: at this stage, what you need is the ability to sort your work orders by status, by date and by work center.
The spreadsheet ceiling comes fast
A work order spreadsheet holds up until someone asks what a delay costs. The day WO-0149 slips two days, a spreadsheet will not reschedule WO-0148, will not reserve the components and will not flag the overloaded work center. That is exactly what production software does.
Quick quiz
Has a work order with status “released” already consumed its components?
What is the life cycle of a work order?
A work order is not a static document. It moves through a sequence of stages, and it carries different information at each one. Here is the full path, from demand to archive.
- Demand appears: a sales order, an inventory level below its reorder point, or a production plan. MRP turns it into a suggested work order.
- Creation records the work order and attaches its technical data: bill of materials, routing, quantity, requested dates.
- Scheduling places it in the plan: which work center, in what sequence, at what priority against the other waiting orders.
- Release hands it to the shop floor and prints what execution needs, in particular the pick list for the stockroom.
- Tracking posts completed quantities, scrap, logged hours and quality checks as the run progresses.
- Closing settles the order: actual is compared to standard, the real cost is calculated and the finished goods are received into stock.
Between those stages the work order changes status, and the status is what tells you how much is really committed. Systems use close variants of the same labels: planned (created, nothing started), released (handed to the floor), in progress (operations running), on hold (temporarily stopped, waiting on a part or a decision), completed (built) and closed (settled and archived).
Closing is the stage most often skipped, and the only one that teaches you anything. It is where you find out whether a routing that promised 12 hours took 18, whether scrap is drifting on one machine, and therefore whether the standard cost behind your quotes still holds.
Looking for software to run your work orders?
Our comparison ranks the best ERP software of 2026, production module and MRP included.
Work order, purchase order, BOM, routing: which does what?
These four show up together constantly in production software, and mixing them up is expensive. The distinction is simple: two are reference data, two are execution orders.
| Concept | Nature | Answers the question |
|---|---|---|
| Bill of materials | Reference data | What is this item made of, and in what quantity? |
| Routing | Reference data | Through which operations, on which work centers, in how long? |
| Work order | Internal execution order | What do we build ourselves, how many, by when? |
| Purchase order | External execution order | What do we buy from a supplier, and for what date? |
What ties the four together is material requirements planning. It starts from the production plan, walks the bill of materials level by level, nets off what is already in stock or on order, then proposes two kinds of releases: a work order for what the company makes, a purchase order for what it buys. On the same bicycle, the wheel gets a work order and the tire gets a purchase order.
That is also why a work order sits at the meeting point of three functions. Production planning decides what to release and when, procurement has to have the components in time, and inventory management and the stockroom have to issue them to the floor. A work order released without its components produces nothing but an idle machine.
How do ERP and MRP systems handle work orders?
Work order management is the core brick of any manufacturing system, whether it comes as a module of a broader ERP or as a dedicated MRP tool. Four options cover small and mid-sized manufacturers well, with very different commercial models. The figures below are list prices recorded on October 16, 2026 from the vendors’ own pages, before negotiated discounts and implementation.
- Dolibarr is an open source ERP whose Manufacturing Orders module ships with the distribution and is enabled in one click: it reuses predefined BOMs to generate orders, and automatically increases stock of produced items while decreasing consumed ones. Free if you self-host. The real limit: scheduling and work center capacity stay rudimentary, and hosting plus upgrades are on you. Our open source ERP roundup covers the trade-off.
- Odoo handles work orders in its Manufacturing app, wired to purchasing and inventory in the same database. Its pricing page, published in euros, lists €19.90 per user per month on the Standard plan with annual billing, €24.90 billed monthly, and €35.90 annually for the Custom plan. The real limit: the free one-app offer will not run a shop, since manufacturing needs inventory and purchasing too, which means a paid plan. See our Odoo review.
- MRPeasy is a cloud MRP aimed at small manufacturers, with manufacturing order tracking from planning to completion listed on the entry plan. Its pricing page starts at $49 per user per month (Starter), $69 for Professional and $99 for Enterprise, with a free trial and no credit card required. The real limit: per-user billing climbs quickly once shop floor operators need their own logins to post time.
- Katana targets shops that sell online and want visual work order control. Its pricing page shows a free plan capped at 30 SKUs, with the Advantage plan quoted on request. The real limit: with no list price on the full offer, the budget is impossible to estimate without talking to sales.
The deciding criterion is neither price nor feature count: it is how the system reschedules when one work order slips. A tool that merely records your orders will not give you much more than a well-kept spreadsheet. If your context is manufacturing in the strict sense, our pick of manufacturing ERP software targets exactly that need.
Next step
To go further, read our best ERP software 2026 comparison, our definition of material requirements planning, which is what generates work orders, or our guide to production planning.
Frequently asked questions
What is a work order in manufacturing?
A work order is the internal document that authorizes a shop floor to build a specific item, in a specific quantity, by a specific date. It carries the item to build, the quantity, the components to consume, the operations to run, the work centers involved and the release and due dates. It is also called a manufacturing order or a production order.
What is the difference between a work order and a purchase order?
A work order covers what the company builds itself: it is internal and addressed to a shop floor. A purchase order covers what it sources outside: it is external and addressed to a supplier. Both are proposed by the same MRP run, which decides item by item whether to make or to buy.
Who creates the work order?
Creation usually sits with planning or production engineering, from an MRP suggestion or a sales order. The production manager approves the release, which is the moment the shop floor actually receives the order. In a small company the same person often does both.
What does it mean to close a work order?
Closing a work order means settling it: you declare good and scrapped quantities, stop posting time and materials against it, receive the finished goods into stock and compare actual to standard. That comparison produces the real cost of the run and the time variances, which feed back into routings and quotes.
Can you manage work orders in Excel?
Yes, as long as the number of simultaneous orders stays low and disruptions are rare. A spreadsheet is fine for listing, sorting and tracking statuses. It cannot reschedule automatically when an order slips, reserve components or flag an overloaded work center. That tipping point is usually what pushes a shop toward MRP software or an ERP production module.
Is a work order the same as a job order or a production order?
In practice yes, the terms overlap. Work order is the broadest, production order and manufacturing order are the ERP labels for the same record, and job order is common in job shops that quote and cost each run separately. The one genuinely different sense is the maintenance work order, which authorizes a repair job rather than a build and is managed in a CMMS.